General Specifications for
NRG COMPANY, INCORPORATED
Chain and Flight Skimmer Equipment

Part 1 - General
1.1 Scope of Work
  Under this item, the Contractor shall furnish and install ___ Conveyor Type Skimmer(s) in ____ Flotation tank(s). Collector equipment to be as manufactured by NRG Company Incorporated or equal. The installation shall be as shown on the drawings and in substantial compliance with these specifications. Each of the ____ mechanisms shall be approximately ___ Wide x ___ feet Long, two shaft systems. Two strands of chain shall run over two sets of sprockets. Fiberglass flight boards equipped with skimming wipers shall be rigidly attached between the chain strands every ten feet for skimming the surface of the tank up and over a curved stainless steel beach located beneath the head shaft.
1.2 Design Criteria
  System design shall be based on dry tank conditions and the following:
    1. Bearing Friction - 0.05 per bearing.
2. Dry friction, UHMW on UHMW - 0.11.
3. Shaft Deflection - less than 3/64 inches per foot at mid-span.
1.3 Experience Qualifications
  The manufacturer of the equipment shall attest to a minimum of 10 years of previous experience in the design and manufacture of non-metallic chain and flight skimmers. A minimum of three installations in operation for more than five years shall be submitted to confirm the requisite experience.
1.4 Bolts and Anchor Bolts
  All flight assembly bolts, nuts and washers shall be ANSI Type 304 stainless steel. Anchor bolts and washers shall be stainless steel and shall comply with the anchor bolts and expansions anchors section.
1.5 Surface Preparation
  All welds shall be thoroughly cleaned and ground smooth in preparation for painting. All ferrous iron and steel surfaces, except motors, speed reducers, chain shall be solvent cleaned in accordance with SSPC-SP1 before shop primer is applied.
1.6 Shop Painting
  All ferrous iron and steel surfaces except motors, speed reducers, chain, and sprockets shall be given a shop coat of the manufacturer's standard rust-inhibitive primer. Field finish coat painting is to be provided by others. Manufacturer's primer to be compatible with the finish coat.
1.7 Power Supply
  Power supply to the equipment will be 230/460 volts, 60 Hz, 3 phase.
1.8 Spare Parts
  The manufacturer shall provide a minimum of _____% (2%) spares of the following components: FRP Flights, Longitudinal chain, Attachment links, filler blocks, wear shoes, sprockets, shear pins, flight hardware, wear strip, and wear strip hardware.